The Closeout Process
Project Work Completed
CCP creates punchlist
Trades complete punchlist
Trades complete punchlist
CCP notifies Architect & Owner of completion
Architect & Owner makes punchlist
The project close out process starts at project kick-off. Completing the project work and punchlist process is only the beginning. Below is additional items provided as apart of the project close out process.
-
Completed Punchlist
-
Certificate of Substantial Completion
-
O&M Manuals
-
Final Inspection and Certificate of Occupancy
-
Testing of completed systems and Start up
-
Spare parts and Extra Materials
-
Keys, Permanent Cylinders and Rekeying
-
Record Drawings
-
Warranties and Guarantees
-
Affidavits of Payments, Lien Releases, and Consent of Surety
-
Training as required by the project
-
Post-occupancy services
Punchlist Completed
Architect issues Certificate of Substantial Completion
CCP completes project
requirements